Timeline

HMR anticipates a ten (10) year timeline for the build-out of their master plan. The following outlines the anticipated development phasing.

The initial phase of construction is planned to entail the North Base lodge/hotel, the mid-mountain lodge, and the new gondola, which replaces the existing Madden chairlift. Subsequent phases will include the balance of the North Base area including new day skier facilities and structured parking, as well as employee housing. Once the initial phases at the North Base are complete, plans call for initiating the redevelopment of the South Base area with a combination of slopeside chalets and a main residential lodge.

Stay tuned for news about the anticipated construction start.

PHASE 1 | NORTH BASE IMPLEMENTATION
Rendering of the Hotel Lodge Entry North Base
  1. Mid Mountain Day Lodge, Hotel/Lodge, Day Skier Services Building and Residential Units, Commercial and Landscape/Ice Pond Area, Workforce Housing and Day Skier Parking Structure, and LEED Commissioning
  2. Residential Building Adjacent to Highway 89
  3. Residential Building Adjacent to Highway 89
Phase 2 | South Base Implementation
Artistic rendering Proposed Condos at Tahoe Ski Bowl South Base
  1. Residential Building (Southern)
  2. Residential Building (Northern)
  3. Townhomes (access from South Base, situated west/Southwest of North Base)
Support Facilities & Environmental Improvements
Homewood shuttle

As is expected with any master planned project there are support facilities and programs as well as environmental improvements that are implemented parallel with the project development. HMR has identified transportation and parking improvements, water quality improvements, forest health and management improvements. The following outlines the phasing of the implementation of these improvements and programs.

Phase 1

  1. All permanent BMPs installed as construction is completed, satellite parking and shuttle services initiated. forest health and fuels reduction project continues and Cumulative Watershed Effects (CWE) is initiated
  2. Scenic enhancement strategies are employed
  3. Continued on-mountain revegetation and erosion control work continues

Phase 2

  1. All permanent BMPs installed as construction is completed
  2. Project Area is fully BMPed, landscaped, revegetated